Previous underground cabling works on Vlaun’s Drive. (NV GEBE file photo)
PHILIPSBURG--NV GEBE and the National Recovery Program Bureau (NRPB) plan to place more than nine kilometres of overhead low-voltage electricity lines underground as part of major infrastructural works set to start in mid-July.
This work is part of the Trust Fund’s Emergency Recovery Project (ERP-1). The St. Maarten Trust Fund is financed by the Government of the Netherlands, managed by the World Bank, and implemented by NRPB on behalf of the government of St. Maarten.
From a budget of approximately US $3.8 million, the work will take place in several phases from July to the fourth quarter of 2022. The road crews of contractor Windward Roads BV will dig trenches on residential streets where overhead cables still exist. These cables, along with new water lines, will be rerouted underground. The work will be carried out under the guidance of GEBE personnel and activity supervisor ILACO Suriname NV.
Empty conduits will also be placed in the trenches, paving the way for the country’s telecommunications companies to lay fibre-optic cables in the future. During the final stages, aluminium streetlight poles will be installed to replace the older wooden ones.
GEBE Acting Temporary Manager Sharine Daniel said this can be seen as a continuation of underground cabling works that were kicked off by the company some years ago and she is pleased to see it being further completed.
“NV GEBE had spent many millions of dollars executing at least 95% of this massive and costly undertaking and the completion of the project will surely benefit our electricity and water grids immensely and, by extension, the community of St. Maarten,” said Daniel.
She further stated that, in 2020, she had finalised GEBE’s decision to upgrade the company’s electricity and water network with resources that were allocated by the Trust Fund Steering Committee to ERP-1. The Trust Fund Steering Committee had set these funds aside in 2018 to support GEBE in building its resilience and restoring material damaged during the 2017 Atlantic hurricane season.
Placing these utility connections underground will expand GEBE’s existing underground network, thereby improving St. Maarten’s resilience to natural disasters such as hurricanes. Underground cables cannot be broken and blown around in a storm’s strong winds, which dramatically reduces the chances of power loss or debris falling on the homes of unlucky residents. It also lessens the time needed to restore electricity, water and Internet connections after a devastating hurricane strike.
These critical services are vitally important in government’s efforts to coordinate post-disaster relief and recovery, as well as in helping citizens return to normalcy.
The underground cabling activity will mostly occur in the Cul de Sac basin, one of St. Maarten’s most densely populated areas.
The scheduled work will start on Spanish Fort Road, Crocus Road, Tassel Drive, Tassel Road, and Lavender Road before moving on to Carnation Road, Amaryllis Road, Gladiola Road, Killebarn Drive, Bleeding Heart Road, Betty’s Estate Road, Flamboyant Road, Orchid Road, Marigot Hill Road, Soursap Road and its surroundings, Mesapple Road, Banana Drive, Genip Road, Guavaberry Road, Peach Road, Beet Road, Cherrynut Road, Pumpkin Drive, Pumpkin Road, and Okra Drive.
Before the start of works, residents will be notified via the media about the activities that will take place on the respective streets. Although most of the work will take place on the public roads, residents with overhead electricity lines running to their homes will be contacted by GEBE about trenching work on their property to connect them to the grid via underground lines. Windward Roads will replace any concrete slabs or foundations damaged by the trenching work and all reconnections will be done by GEBE technicians.
Vigorous safety protocols will be put in place to minimise the inconvenience to residents. For example, safe crossings will be placed over trenches in front of driveways and walking paths to ensure accessibility to homes and businesses. Additionally, a traffic plan has been developed to help alleviate potential congestion for motorists.
However, residents may experience increased noise and/or dust between the working hours of 7:00am and 5:00pm on weekdays. The availability of electricity and water will not be interrupted, except during the connection to the new underground system after the completion of works.
“Neighbourhoods devoid of underground cabling were left for many weeks without electricity after the passing of Hurricane Irma, while other neighbourhoods that were supplied via the underground network regained service just days after the devastation,” said NRPB Director Claret Connor.
“This project is yet another step being taken to ensure that, in the event of a future hurricane, or other unfortunate disasters, the residents and small businesses in this very densely populated area of St. Maarten will be able to bounce back quicker than in 2017.”
Minister of Public Housing, Spatial Planning, Environment and Infrastructure VROMI Egbert Doran considers this project to be a great feat.
“As we continue to be threatened by hurricanes, the bounce-back period after a devastation is of great importance, not only for our personal resurgence but also for the island’s economic recovery,” said Doran. He added that the inconvenience of the works will be minor in comparison to the project’s long-term benefits and asks the public to be patient and considerate during the period that the works will be ongoing.
For more information about the underground cabling activity, persons can visit
www.nrpbsxm.org/undergroundcabling.
After the work has started, if anyone has an issue or grievance related to the activity, they can file a complaint via the form on
www.nrpbsxm.org/complaints-procedure, or by contacting the Windward Roads complaint representative at tel. 1721-5427520 or by sending an e-mail to
This email address is being protected from spambots. You need JavaScript enabled to view it..